
Mountain Villas Resort Homeowners' association








THE BEAUTY OF FALL IS UPON US.
HOWEVER, PROJECT WORK IS NEVER DONE TO MAINTAIN OUR CAPITAL INVESTMENT.
​
-
BUILDING 2 IS NOW UNDERGOING BRICKWORK REPAIRS AND CONDO DOORS ARE BEING PAINTED.
-
BALCONY WOOD REPAIRS, REPLACEMENT, AND PAINTING ARE ALSO IN FULL OPERATION.
-
FALL CLEANUP IS UNDERWAY. THE CONTRACTOR ALSO CLEARED SOME BRANCHES FROM THE BUILDINGS AND POLE LIGHTS.
-
AN ARBORIST DID SOME TREE TRIMMING AND SHAPING AND WE REMOVED THE DEAD PINE TREES COMING UP THE
RIGHT-HAND SIDE OF THE DRIVEWAY. THE SPLIT RAIL FENCE WAS ALSO REPAIRED.
-
IF THAT WASN'T ENOUGH, THE OFFICE ROOF JUST COULDN'T TAKE ANY MORE PUNISHMENT FROM THE ELEMENTS. ONCE IT STARTED LEAKING, WE COULDN'T IGNORE IT ANYMORE. THE ROOF IS BEING REPAIRED AND A NEW METAL ROOF INSTALLED.
​​​





CHANGES AT THE PRO SHOP - TEE TOP LOUNGE
Construction at the Tee Top Lounge is moving forward with the excavation for the foundation of the new addition. Over the winter that side deck was demolished to make room for this new addition.
The Tee Top is open 9:00 AM to 5:00 PM , 7 days a week. The hours may change throughout the year. (To Be Announced)
There are numerous specialty cocktails as well as four additional boards displayed in the Tee Top. Their register software has been switched over; they still accept cash and all credit cards.


Building 5 - Board and Batten Siding is Complete!​
Building 6 - Board and Batten Siding is Complete - July 2023!
Building 7 - Board and Batten Siding is Complete - June 2024!
​
It has been a long process getting the townhouses upddated and looking great. We thank all the staff at Big Fish for their skill and expertise in getting this major project accomplished.
​
Here's the photo timeline view of Building #7
https://api.companycam.com/timeline/QfVFuXpDNRDVptFC
​
2022 Major Projects
Planned/Completed
​
Bldg 5 - Installation of Board & Batten Siding and Gutters.
Work Completed
Condo steps repaired - all buildings - Work Completed
Emergent work on stairways and T1-ll repairs. Work Completed
Bldg 1 (back) - Siding and brickwork. Work Completed
Bldg 2A/B - Repaired leaking roof. Work Completed
​
Parking lot repaving may be deferred for 2023 as defined in the Reserve Study Schedule.
​
Replace trees where older ones were removed.
2023 Major Projects
Planned/Completed
​
Bldg 6 - Installation of Board & Batten Siding and Gutters - Work Completed.
Bldg 1 (back) - Work Completed.
Bldgs 6 and 7 - Brick Replacement and repair. Work Completed.
​
Parking lot repaving may be deferred to 2024. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority.
​
Parking lot has been repaved and striped to give us some time to finish out the repairs to our buildings.
​
​
​
​
2024 Major Projects
Planned/Completed
​
​Bldg 7 - Board & Batten siding for Building 7 - Work Completed.
Bldg 7 - More brick repair, focusing on Building 7 - Work Completed.
Bldgs 1, 2, 3, 8 and 9 - Finish the back roofs. - Work Completed.
Front Entrance Sign - Paint and freshen up. - Work Completed
​
Parking lot repaving may be deferred to 2025. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority.
​
​
​
​
​
​
2025 Major Projects
Planned
​
​Bldgs. 8 and 9 - More brick repair, focusing on Bldgs. 8 and 9. Brickwork also needed on Bldg. 2.
Common Areas - Repair and painting of all doors and windows in common areas. - Ongoing
Common Areas - Install security cameras as the budget allows.
All Buildings - Balcony wood repair, replacement, and painting. - Ongoing
Pool Area - Replace the sidewalk going to the main pool gate.
​
​
Parking lot repaving may be deferred to 2026/2027. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority and we are again building up our Reserves to fund the work.​​​​​​


