Mountain Villas Resort Homeowners' association








WINTER IS ALMOST BEHIND US - AND MUCH HAS BEEN ACCOMPLISHED.
HOWEVER, PROJECT WORK IS NEVER DONE TO MAINTAIN OUR CAPITAL INVESTMENT.
​
-
THE NEW OFFICE ROOF WAS COMPLETED JUST IN TIME FOR THE BRUTAL WINTER.
-
BUILDING 2 WILL CONTINUE UNDERGOING BRICKWORK REPAIRS ALONG WITH BUILDINGS 8 AND 9.
-
BALCONY WOOD REPAIRS, REPLACEMENT, AND PAINTING WILL ALSO CONTINUE IN FULL OPERATION.​​
-
SPRING CLEANING HAS BEGUN. LOTS OF WORK TO DO, BUT DON'T WANT TO GET TOO AHEAD OF THE GAME JUST IN CASE "WINTER" ISN'T OVER QUITE YET AND WE NEED TO DO THE WORK TWICE.
-
THE CABANA AND OFFICE DECK HAVE BEEN PRESSURE WASHED IN PREPARATION FOR STAINING.
-
TWO MORE MONTHS UNTIL POOL OPENS.





CHANGES AT THE PRO SHOP - TEE TOP LOUNGE
Construction at the Tee Top Lounge is moving forward with the excavation for the foundation of the new addition. Over the winter that side deck was demolished to make room for this new addition.
The Tee Top is open 9:00 AM to 5:00 PM , 7 days a week. The hours may change throughout the year. (To Be Announced)
There are numerous specialty cocktails as well as four additional boards displayed in the Tee Top. Their register software has been switched over; they still accept cash and all credit cards.


Building 5 - Board and Batten Siding is Complete!​
Building 6 - Board and Batten Siding is Complete - July 2023!
Building 7 - Board and Batten Siding is Complete - June 2024!
​
It has been a long process getting the townhouses upddated and looking great. We thank all the staff at Big Fish for their skill and expertise in getting this major project accomplished.
​
Here's the photo timeline view of Building #7
https://api.companycam.com/timeline/QfVFuXpDNRDVptFC
​
2023 Major Projects
Planned/Completed
​
Bldg 6 - Installation of Board & Batten Siding and Gutters - Work Completed.
Bldg 1 (back) - Work Completed.
Bldgs 6 and 7 - Brick Replacement and repair. Work Completed.
​
Parking lot repaving may be
deferred to 2024. The Reserve
Study initially recommended scheduling the work in 2023.
Crucial work on our capital investments (buildings) have taken priority.
​
Parking lot has been repaved and striped to give us some time to finish out the repairs to our buildings.
​
​
​
​
2024 Major Projects
Planned/Completed
​
​Bldg 7 - Board & Batten siding for Building 7 - Work Completed.
Bldg 7 - More brick repair, focusing on Building 7 - Work Completed.
Bldgs 1, 2, 3, 8 and 9 - Finish the back roofs. - Work Completed.
Front Entrance Sign - Paint and freshen up. - Work Completed
​
Parking lot repaving may be deferred to 2025. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority.
​
​
​
​
​
​
2025 Major Projects
Planned
​
​Bldgs. 8 and 9 - More brick repair, focusing on Bldgs. 8 and 9. -
Ongoing
Brickwork also needed on Bldg. 2.
Common Areas - Repair and painting of all doors and windows in common areas. - Ongoing
Common Areas - Install security cameras as the budget allows.
All Buildings - Balcony wood repair, replacement, and painting. - Ongoing
Pool Area - Replace the sidewalk going to the main pool gate.
​
​
Parking lot repaving may be deferred to 2026/2027. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority and we are again building up our Reserves to fund the work.​​​​​​
2026 Major Projects
Planned
​
​Bldgs. 8 and 9 - More brick repair, focusing on Bldgs. 8 and 9. -
Ongoing
Brickwork on Bldg. 2 - Ongoing.
Common Areas - Repair and painting of all doors and windows in common areas. - Ongoing
Office Roof - Damage required a new roof. Metal roof was installed. Work Completed
All Buildings - Balcony wood repair, replacement, and painting. - Ongoing
Common Areas - Install security cameras as the budget allows.
Pool Area - Replace the sidewalk going to the main pool gate as the budget allows.
​​​
Parking lot repaving may be deferred to 2026/2027. The Reserve Study initially recommended scheduling the work in 2023. Crucial work on our capital investments (buildings) have taken priority and we are again building up our Reserves to fund the work.​​​​​​